Friday, February 7, 2014

Filled Under:

discharged by frustration

A contract may be discharged by frustration. A contract may be frustrated where there exists a change in circumstances, after the contract was made, which is not the fault of either of the parties, which renders the contract either impossible to perform or deprives the contract of its commercial purpose. Where a contract is found to be frustrated, each party is discharged from future obligations under the contract and neither party may sue for breach. The allocation of loss is decided by the Law Reform (Frustrated Contracts) Act 1943.

Examples of frustrating events

Destruction of the subject matter

Personal incapacity will generally render the contract frustrated

Where the contract becomes illegal to perform it will frustrate the contract

Where a contract can not be performed in the specified manner

A contract may also be frustrated where it is deprived of its commercial purpose

However, the contract must be deprived of the whole commercial purpose to amount to frustration

No frustration

A contract will not be frustrated where:

    It is more difficult or expensive to perform
    Impossibility of performance is the fault of either of the parties
    Where there is a force majeure clause
    Where the frustrating event could be foreseen

1. A contract will not be frustrated merely because it becomes more difficult or expensive to perform:

2. A contract will not be frustrated if the impossibility is the fault of either of the parties:

3. Where there exists a force majeure clause this will apply rather than the law of frustration. The clause must actually cover the event which occurred:

4. Frustration will also not exist where the frustrating event should have been foreseen:

Affect of frustration of a contract:
-Where a contract is found to be frustrated, both parties are released from their obligations under the contract and neither party may sue for breach.
-The allocation of loss is decided by the Law Reform (Frustrated Contracts) Act 1943. This provides:
-s.1(2) All money payable under the contract ceases to be payable and any money already paid may be recovered. Where expenses have been incurred this may be deducted from the amounts payable or paid. This is at the discretion of the court and is subject to what is just and equitable in the circumstances of the case. There is no provision allowing expenses to be recovered which exceed the amounts paid or payable.
-S.1(3) - Where a valuable benefit has been conferred this must be paid for.

0 comments: